Buildings that use Exact Layout.

Concrete buildings in Naples and Sarasota where Exact Layout prepared the drawings, put them on the crew's iPads and built 3D models of the structure.

Project

Encore

Naples, Florida

A concrete building in Naples. Every floor's framing drawings, both wings, were lined up with each other for the crew, with control points, blockouts and control joints placed on the drawings, ready for layout.

  • Every floor lined up, both wings
  • Control points, blockouts and control joints
  • Feet and inches, on the drawing
Encore from a drone: white buildings around a pool courtyard, with the water and the town behind
Encore's pool courtyard and terraces from a drone
Encore's floor framing drawings stacked in 3D, floor over floor
Project

3300

Naples, Florida Currently in progress

A concrete mid-rise on the water in Naples, one of three buildings on the job. The structure is in a 3D model with the rebar and post-tension cables, the job's daily log shows the building day by day, and every floor's drawings are lined up for the crew and the office.

  • 3D BIM with rebar and PT
  • Progress by day
  • Drawings lined up floor by floor
The building in 3D with the rebar and post-tension cables showing through the concrete, floor by floor
The job site at sunrise from a drone, with the deck, the crane and the water
A post-tension deck seen straight down before the pour, with the pink tendons and the crew
Project

The Edge

Sarasota, Florida

A concrete high-rise on the bay in Sarasota. The layout gridlines, the slab-edge embed plates and the railing blockouts for the upper floors were placed on the job's drawings, ready for the crew.

  • Layout gridlines on the drawings
  • Slab-edge embed plates and railing blockouts
  • Feet and inches, on the drawing
A concrete deck pour on The Edge seen from a drone, with the crew and the pump boom
Project

Siesta Hotel

Sarasota, Florida Currently in progress

A six-story concrete hotel on Siesta Key. The job's drawings are kept up to date on the iPad, the structure is in a 3D model from the foundation to the roof, and the pile as-built locations are in one report for the engineer.

  • Drawing updates on the iPad
  • 3D model of the structure
  • Pile as-built report
The hotel's structure in 3D: two wings, six floors of slabs, columns and walls

Want to see it on your job?

Apply, and our team will send you examples from real jobs.